Moyer v. Lasher Construction, Inc.
In 2014, Casey Moyer entered into an agreement with Doug Lasher Construction, Inc. for the construction and purchase of a new home, which was substantially completed in November 2014. Over the next six-and-a-half years, Moyer repeatedly informed Lasher Construction about issues with the home, particularly water leakage, and received assurances that the issues would be fixed. However, the problems persisted, and Moyer and Caitlin Bower filed suit against Lasher Construction in November 2021, alleging breach of contract and violation of the Idaho Consumer Protection Act.The District Court of the Fourth Judicial District of Idaho granted summary judgment in favor of Lasher Construction, ruling that all claims were time-barred under Idaho Code sections 5-241(b) and 5-216, which require that claims arising out of a contract for the construction of real property be brought within five years of the final completion of construction. The court also found that the Idaho Consumer Protection Act claims were time-barred under the two-year statute of limitations provided by Idaho Code section 48-619. The court rejected the homeowners' arguments for equitable estoppel and the repair doctrine, concluding that they failed to show that Lasher Construction prevented them from pursuing their claims within the statutory period.The Supreme Court of Idaho affirmed the district court's decision. The court reaffirmed that the repair doctrine is not available in Idaho and upheld the district court's conclusion that the homeowners failed to establish the elements of equitable estoppel. The court also agreed that the text messages and the July 2, 2021, response to the NORA demand did not constitute enforceable independent contracts. Lasher Construction was awarded attorney fees and costs on appeal as the prevailing party. View "Moyer v. Lasher Construction, Inc." on Justia Law
Genho v. Riverdale Hot Springs, LLC
Daniel Genho and Riverdale Hot Springs, LLC had a dispute over payment for construction work Genho performed at Riverdale Resort. Genho was not a registered contractor at the start of the project but became registered midway through. Riverdale refused to pay Genho and prevented him from retrieving his tools and materials. Genho filed a Mechanic’s and Materialmen’s Lien and sued for breach of contract, unjust enrichment, quantum meruit, conversion, and to foreclose on the lien.The District Court of the Sixth Judicial District of Idaho granted Riverdale’s motion for a directed verdict on the breach of contract claim but denied it on the other claims. The court found that there were two separate transactions: one before and one after Genho became a registered contractor. The court allowed the jury to consider the unjust enrichment, quantum meruit, conversion, and lien foreclosure claims. The jury found in favor of Genho, awarding him $295,568, which was later reduced to $68,681. The district court also awarded attorney fees to Genho.The Supreme Court of Idaho reviewed the case and affirmed the district court’s decision in part and reversed it in part. The court held that equitable remedies are available under the Idaho Contractor Registration Act (ICRA) for work performed after a contractor becomes registered, provided the work is severable from the unregistered work. The court affirmed the denial of a directed verdict on the unjust enrichment, quantum meruit, and lien foreclosure claims but reversed the award of attorney fees for the conversion claim, as it was not based on a commercial transaction. The court also affirmed the award of attorney fees for the foreclosure action under Idaho Code section 45-513. Neither party was awarded attorney fees on appeal. The judgment was vacated and remanded for modification consistent with the opinion. View "Genho v. Riverdale Hot Springs, LLC" on Justia Law
Pinkham v. Plate
The case involves Scott and Natalie Pinkham, who contracted with Three Peaks Homes, LLC, for the construction of a custom home. The construction did not go as planned and the contract was terminated before the home was completed. Three Peaks subsequently filed two $600,000 mechanics’ liens against the Pinkhams’ home. The Pinkhams then filed a complaint against David Plate, Rebeccah Jensen, Three Peaks, Rebel Crew Construction, LLC, and Legacy Management Enterprises, LLC, asserting several causes of action.The district court denied the Pinkhams’ motion for summary judgment. Later, the Pinkhams’ attorney, Lance Schuster, filed a motion to withdraw as counsel for Plate, Jensen, Three Peaks, and Legacy, which the court granted. The court ordered Appellants to appoint another attorney or appear in person within twenty-one days of service of the order, failing which, the court may enter default judgment against them. The court clerk served a copy of the withdrawal order on Appellants via first class mail.The Pinkhams moved for the entry of default and default judgment against Appellants and for dismissal of Appellants’ counterclaims with prejudice. The district court granted the Pinkhams’ motion without a hearing. Appellants later secured new counsel and filed a motion to set aside the default and default judgment under Idaho Rule of Civil Procedure 60(b)(1), (4), and (6). The district court denied Appellants’ motion.On appeal, the Supreme Court of the State of Idaho affirmed the district court’s decision denying the motion to set aside the default and default judgment. The court held that the district court did not err in concluding that Appellants failed to demonstrate good cause to set aside the entry of default. The court also held that Appellants have failed to establish a right to relief under Rule 60(b). The court declined to award attorney fees on appeal. View "Pinkham v. Plate" on Justia Law
Datum Construction, LLC v. Re Investment Co.
In this case, the Supreme Court of the State of Idaho was required to interpret aspects of Idaho’s mechanic’s lien statutes. Datum Construction, LLC, was the general contractor for a commercial construction project, and subcontracted part of the work to Elmore Welding and Steel, who rented equipment from RE Investment Co., LLC, dba Pro Rentals & Sales. Elmore Welding and Steel failed to pay Pro Rentals for the equipment rental, resulting in Pro Rentals filing a mechanic's lien. Datum then purchased a bond and petitioned the district court to release the lien. Pro Rentals did not oppose this petition and the district court released the lien. Datum argued that Pro Rentals had failed to begin proceedings to enforce its claim of lien within six months. The district court granted Datum’s motion to release the bond. Pro Rentals appealed this decision.The Supreme Court of the State of Idaho ruled in favor of Pro Rentals, determining that the district court had erred in applying a six-month statute of limitations from the mechanic’s lien statutes to a bond action. The court held that the bond replaced the lien, and the six-month period to enforce a lien was not applicable once the lien was released. The court determined that the appropriate statute of limitations for an action against the bond was two years under Idaho Code section 5-219. Therefore, the court reversed the district court’s decision to release the bond. View "Datum Construction, LLC v. Re Investment Co." on Justia Law
Shake Out, LLC v. Clearwater Construction, LLC
Shake Out, LLC entered into a contract with Clearwater Construction, LLC (“Clearwater”), to repair the building Shake Out’s restaurant occupied. The relationship between the parties quickly deteriorated, resulting in Shake Out filing a lawsuit against Clearwater. The parties attempted to mediate their dispute but were unsuccessful. After the case had proceeded for some time, Clearwater sought to compel arbitration pursuant to the contract. Shake Out objected, asserting that Clearwater had waived its right to enforce the arbitration clause because it had participated in the litigation for almost ten months before seeking to compel arbitration. The district court concluded Clearwater had not waived its right to seek arbitration and entered an order compelling arbitration and staying the proceedings. Finding no reversible error in that judgment, the Idaho Supreme Court affirmed. View "Shake Out, LLC v. Clearwater Construction, LLC" on Justia Law
Eagle Rock Timber, Inc. v. Teton County
After submitting the winning bid, Eagle Rock Timber, Inc. (“Eagle Rock”), contracted with Teton County, Idaho to reconstruct a stretch of road known as “Chapin Lane.” During the course of the project, Eagle Rock claimed it discovered unsuitable base material under portions of the road. Eagle Rock maintained that Teton County’s agent, Darryl Johnson, directed Eagle Rock to remove the material and said that the county would “make it right.” However, when Eagle Rock attempted to recover an amount in excess of the original Contract Price, Teton County denied Eagle Rock’s request, stating that it had not authorized any changes to the Contract. When the parties could not resolve this dispute over the amount owed, Eagle Rock filed suit. Teton County twice moved for summary judgment. The district court denied the first motion, concluding that genuine issues of material fact existed concerning whether Johnson orally waived the writing requirement and whether Johnson had authorized Eagle Rock to remove the unsuitable base material, which could support an equitable remedy. In the County's second motion, the district court granted it, ruling that since Teton County’s agent did not have actual or apparent authority to bind Teton County, the claims asserted by Eagle Rock failed as a matter of law. Eagle Rock appealed, asserting that the district court erred because there were still genuine issues of material fact that should be resolved by a jury. Further, Eagle Rock claimed the district court’s refusal to grant leave to amend its complaint to assert a separate cause of action against Johnson personally was an abuse of discretion. After review, the Idaho Supreme Court reversed the district court’s grant of summary judgment and denial of leave to amend. However, the Court affirmed the district court in not considering the ratification issue because it was beyond the scope of the pleadings at the time it was presented. View "Eagle Rock Timber, Inc. v. Teton County" on Justia Law
BrunoBuilt, Inc. v. Erstad Architects, PA
The issue this case presented for the Idaho Supreme Court's review centered on a residence in the Boise foothills that was damaged by a landslide, which ultimately prevented the builder from obtaining a certificate of occupancy. BrunoBuilt, Inc., the general contractor of the project, sued multiple parties, including Erstad Architects, PA, the architectural firm for the project, Andrew Erstad, the principal architect, and Cheryl Pearse, the project manager from Erstad Architects, PA (collectively, Defendants), for professional negligence in connection with work completed for construction of the residence. Defendants successfully moved for summary judgment on the basis that the two-year statute of limitations in Idaho Code section 5-219(4) barred BrunoBuilt’s claim. Two years after the district court issued its memorandum decision and order granting summary judgment, BrunoBuilt moved the district court for reconsideration, citing new evidence and arguments. The district court denied the motion for reconsideration, concluding it was “untimely, lacking in diligence, and improper.” BrunoBuilt then appealed, challenging the decision of the district court on summary judgment and additionally asserting that the court erred in an earlier order deconsolidating the cases with other defendants. Prior to oral argument, Defendants moved the Supreme Court to sanction counsel for BrunoBuilt pursuant to Idaho Appellate Rule 11.2 for non-disclosure of material procedural facts in its opening brief. After review, the Supreme Court affirmed the district court’s decision granting summary judgment against BrunoBuilt, and agreed that the conduct of BrunoBuilt’s attorney on appeal ran afoul of Rule 11.2, and imposed sanctions. View "BrunoBuilt, Inc. v. Erstad Architects, PA" on Justia Law
Brunobuilt, Inc. v. Briggs Engineering, Inc.
BrunoBuilt, Inc., was constructing a custom home on a vacant lot in 2016 when a landslide occurred beneath the Terra Nativa subdivision in the Boise foothills. Following damage to the lot, BrunoBuilt filed a professional negligence suit against numerous engineers and engineering firms involved in the construction of the subdivision, arguing that they failed to identify preexisting landslide conditions and other geological circumstances that made residential development unsafe at this site. In the fall of 2018, BrunoBuilt discovered additional damage to the finished custom home itself. It then brought suit against additional defendants, including Briggs Engineering, Inc., and Erstad Architects. Briggs Engineering moved for summary judgment, which the district court granted. The court concluded that BrunoBuilt’s action was time barred by the two-year statute of limitations under Idaho Code section 5-219(4). BrunoBuilt appealed this decision, arguing that the malpractice claim did not begin to accrue until there was damage to the custom home, rather than just the land. To this the Idaho Supreme Court disagreed with BrunoBuilt’s analysis and affirmed the district court that BrunoBuilt’s claim was time barred. View "Brunobuilt, Inc. v. Briggs Engineering, Inc." on Justia Law
Idaho v. Clapp
Tyler Clapp appealed his conviction for driving under the influence. After stopping Clapp for “spinning cookies” in a parking lot, police became suspicious that Clapp was intoxicated. Clapp refused to submit to any field sobriety tests. Police then obtained a warrant for a blood draw, which showed that Clapp’s blood alcohol content (“BAC”) was 0.152 several hours after initially detaining him. At trial, the State sought to introduce the results of the blood draw. Over Clapp’s objection, the district court allowed the nurse who conducted the blood draw to testify telephonically to his qualifications in order to lay sufficient foundation to admit the results of the blood draw. The results of the blood draw were ultimately admitted, and the jury convicted Clapp of driving under the influence. Clapp appealed. The Idaho Supreme Court found the telephonic testimony violated Clapp’s right to confrontation, "'the face-to-face confrontation requirement is not absolute does not, of course, mean that it may be easily dispensed with. ... [A] defendant’s right to confront accusatory witnesses may be satisfied absent a physical, face-to-face confrontation at trial only where denial of such confrontation is necessary to further an important public policy and only where the reliability of the testimony is otherwise assured.' Both requirements must be met." Further, the Supreme Court determined the State failed to meet its burden establishing harmless error. The conviction was vacated and the matter remanded for further proceedings. View "Idaho v. Clapp" on Justia Law
Walker v. Meyer
Brent Meyer appealed pro se a district court’s judgment granting Adam Walker’s breach of contract claim against him. Walker hired Meyer to assist him with the demolition and remodel of a home he had purchased in Soda Springs, Idaho. Walker alleged that in June 2018, the parties entered into an agreement in which Walker agreed to pay Meyer $18,000 in exchange for Meyer’s labor on the home. This contract was subsequently modified by the parties as Meyer performed work on other areas of the home not covered by the contract and Walker paid Meyer more money than provided in the original contract – roughly $60,000. On October 16, 2018, Walker fired Meyer from the job, alleging the labor was not up to industry standards and did not add value to the home. Walker hired another contractor to fix or redo the work completed by Meyer and his subcontractors. Meyer argued the district court erred in concluding he was not a “construction professional” as defined by Idaho’s Notice and Opportunity to Repair Act (“NORA”), Idaho Code sections 6-2501–04, and claimed the case should have been dismissed because Walker failed to comply with the notice requirement of NORA. Finding no reversible error, the Idaho Supreme Court affirmed the district court. View "Walker v. Meyer" on Justia Law